Our Mission

Client: East London Surgeries
Value: £800,000
Duration: June 2015 - March 2016

GP Surgeries


Key Features

  • Etec were contracted to undertake internal refurbishments to several surgeries in East London
  • This included a full strip out including electrics and data supplies along with removing partition walls to create the new layout as required
  • Following remodelling we carried out a full fit out including power and data to the new reception counters and consultancy rooms
  • The consultancy and reception areas were redesigned with the users in mind including medical equipment, storage, and filing areas
  • The surgeries were situated in busy residential and high street areas
  • This meant that traffic management was important to minimise disruption and prevent delays to the programme
  • Where possible we used the on site parking for storage making the most of 'just in time' delivery methods to minimise storage requirements

 

Challenges and Solutions

  • The project was challenging with the surgeries remaining open during the project
  • To manage the works in the occupied building careful phasing was required
  • Demolition was carried out on weekends, other tasks were carried out early in the morning before the surgery opened and
  • Full segregation was in place to protect the public from the works
  • Where required we also created alternate access arrangements