Kingston Mortuary Chapel

Kingston Mortuary Chapel Case Study

Key Features

Etec delivered the design and build restoration of the historic Kingston Mortuary Chapel for the Royal Borough of Kingston between June 2025 and March 2026 (36 weeks). The project preserved and stabilised this listed building, dating back to the 1800s.

Works included underpinning the unstable chapel, carefully dismantling and rebuilding sections of stone walls and buttresses using original and reclaimed materials, installing replacement stained glass windows, remedial roof repairs, replacement internal render, and new limestone slab flooring.

Due to the building’s heritage status, close coordination with structural engineers and the client’s conservation advisors was required to maintain the chapel’s historic character.

Challenges and Solutions

The project faced several challenges due to the building’s age and condition. Originally planned as a 16 week scheme, it became clear the structure was in worse condition than reported. Some walls were at risk of collapse, requiring a temporary works plan and exclusion zones to protect operatives.

Rotten roof timbers were discovered, and due to the listed status, additional planning consent was needed for repairs, affecting the programme. The combination of structural instability and heritage sensitivities required enhanced health and safety measures throughout the works.

Innovations

The project highlighted the importance of early and thorough structural surveys for heritage buildings.

Close collaboration with structural engineers and conservation advisors proved essential, particularly for temporary works and stabilisation.

It also reinforced the need for flexibility in programme planning, as unforeseen issues and listed building requirements can impact timelines.

The project maintained a positive relationship with the Client Advisor, with the potential for a client reference if required.

Client

Royal Borough of Kingston

Value

£600,000